PHOTO: NGCP logo superimposed on a power supply station FOR STORY: NGCP gets green light for P2.58-B Capas substation

The Energy Regulatory Commission (ERC) gave its go signal for the proposed P2.58-billion substation project of the National Grid Corp. of the Philippines (NGCP) in Tarlac province.

Based on a document from the ERC, the project could help support the anticipated increase of power load in Capas town amid the connection to the grid of Shin Clark Power Corp.— the distribution utility for New Clark City (NCC)—as well as Tarlac Electric Cooperatives I and II and Tarlac Electric Inc.

Article continues after this advertisement

“The proposed Capas 230 kV (kilovolt) substation project aims to manage this growth and facilitate NCC’s connection to the Luzon grid,” the ERC said.

FEATURED STORIES BUSINESS BIZ BUZZ: Surprise! MVP revives Smart Money BUSINESS SEC extends ECIP applications until end of 2024 BUSINESS Pogo phaseout in full swing; only 17 remain

However, the regulator said that the project was still “subject to optimization during [an upcoming reset of regulations], based on its actual use and usefulness and verified expenses for the optimized assets.”

READ: NGCP earmarks ₱600B for grid projects

Article continues after this advertisement

READ: NGCP fined P3.5M for ‘unjustified’ project delays

Article continues after this advertisement

According to a report from the NGCP, supply for the increased demand would come from the Concepcion 230 kV Substation through the proposed Concepcion–Capas 230 kV Line.

Article continues after this advertisement

Last month, the ERC also green-lighted the construction of three more projects of the NGCP worth a total of P38.09 billion.

These are the Bolo-Balaoan 500 kV Transmission Line Project, the Northern Luzon 230 kV Loop Project, and the Nabas-Caticlan-Boracay Transmission Project.

Dimalanta earlier said it was crucial for NGCP to ensure the efficient and timely completion of the projects in order to absorb new power capacities that are needed to meet the growing demand.

—LISBET K. ESMAEL Your subscription could not be saved. Please try again. Your subscription has been successful.

Subscribe to our daily newsletter

SIGN ME UP

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.megapanalo

READ NEXT Maynilad expects to deliver record high earnings this 2024 IWG to expand PH flexible office portfolio by 50% EDITORS' PICK Sofronio Vasquez named ‘The Voice’ Season 26 winner Malibu fire destroys homes, forces evacuations and school closures Biden says Trump economic plan will be 'disaster' UAAP Finals: La Salle beats UP in tense finish to force Game 3 DTI gives shopping tips for the holiday season Isko Moreno’s legacy of public markets in Manila MOST READ Comelec OKs additional provincial council seats in 21 provinces VP Sara Duterte considering hiring private security force Isko Moreno’s legacy of public markets in Manila UAAP Finals: La Salle beats UP in tense finish to force Game 3 Follow @FMangosingINQ on Twitter --> View comments